Peru's energy and mines ministry has granted Huayra Kallpa and Perú Energía Renovable temporary concessions for wind power generation projects.
Huayra, which submitted requests for the concessions in June, has 24 months to carry out feasibility studies for the Bella Unión and Punta Balcones projects, each of which would boast 200MW, the official gazette reported.
Studies will be carried out at in Arequipa region for Bella Unión and Piura for Punta Balcones.
For its part, Perú Energía Renovable, which submitted its concession requests in July, has two years to carry out feasibility studies for the Casma I (100MW) and Chimbote I (100MW) projects in Ancash region and Huacho I (100MW) in Lima region.
Earlier this year, the ministry awarded Perú Energía Renovable temporary concessions for wind projects Marcona I (100MW), La Pampa (100MW), Talara (300MW), Ilo 1 (200MW) and Ascope (100MW).